Work Sequence: Phase 2B >>> Phase 2A

Phase 2B

Contractor will start with 2 crews, both working south along the east side of the street in Phase 2B.
One crew will start at Benning Road, NE on the east side of the street and work south towards East Capitol Street.
Second start point is Isherwood Street, NE.
Work is expected to take 2-3 weeks per block per side, meaning east side and west side of the street.
The contractor will stagger their crews and will start with electrical and storm drain piping work first.
Two to three weeks after those crews start, the civil crews will be coming behind them in each block. Civil work will include sidewalks, alley entrances, curb and gutter, ADA ramps, and flexible paving at locations with trees.

Phase 2A

Once the east side from Benning to Isherwood is complete, crews will start from Benning Road NE and start work along the west side of the street for Phase 2A.
Multiple mobilizations will be required for each block due to the variety of work involved and the fact that some of the work such as the street lighting and traffic signals needs to be coordinated with PEPCO.
Any work from C Street NE to East Capitol Street and from East Capitol Street SE to Potomac Avenue SE is dependent on coordination with ongoing utility work in those areas and schedule is to be determined.

Any work from C Street NE to East Capitol Street and from East Capitol Street SE to Potomac Avenue SE (Phases 1A and 1B) is dependent on coordination with ongoing utility work in those areas and schedule is to be determined.