PROJECT BACKGROUND

The 17th Street Project involves traffic calming measures, landscaping, and utility work along 17th Street from Benning Road NE to Potomac Avenue SE, and extending south from Potomac Avenue SE to Barney Circle SE (pavement markings only).

 

The project is both federal and District-funded.  Capitol Paving was awarded the contract on October 17, 2016.  DDOT issued a Notice to Proceed with contract work to Capitol Paving on January 31, 2017. The estimated completion date for the project is July 24, 2018 which is a duration of 540 calendar days.

 

DDOT also issued a Notice to Proceed to Daniel Consultants, Inc. for construction management and inspection services on December 19, 2016 with a completion date of August 11, 2018 (duration of 600 calendar days).